Project: EAST MISSION BAY (NORTH) NRP PIPELINE PROJECT
Client: City of San Diego
Location: San Diego, California
Services:
  • Identification and location of existing utilities
  • Technical Specifications
  • Identification of required permits and the development of a Permit Work Plan and Schedule which included:
      Section 404 Permits, U.S. Army Corps of Engineers
      Stream Alteration Permits, Dept. of Fish and Game
      San Diego Air Quality Management District Permit
      Regional Water Quality Control Board Permits
      Coastal Commission Permits
      City of San Diego Permits and Approvals
  • Other Approvals and Permits
      Pacific Bell
      CalOSHA
      CALTRANS
      AT&SF Railroad
      County Health Department
      San Diego Gas & Electric
  • Permit Applications and Technical Backup
      Air Quality Control Plan
      Hazardous Material Management Plan
      Engineering and Technical Reports
      Noise Abatement Plan
      Risk Management and Prevention Plan
      Wetlands Mitigation Plan



  • Details

    Dean Ryan's California licensed Professional Engineers were involved in: preparing draft specifications, incorporating written directions by the City, preparation of permit work plans and schedule, permit applications; air quality control plan, hazardous material management plan; engineering and technical report preparation; noise abatement plan; risk management and prevention plan; wetlands mitigation plan and other permit requirements.

    During the design phase, Dean Ryan determined the locations and evaluations of existing public and private utilities including horizontal and vertical locations of public and private utilities on preliminary, final plan and profiles. Dean Ryan personnel then developed a list of existing utilities that required exact horizontal and vertical locations for final design. Dean Ryan then developed a construction cost estimate for the relocation of utilities.

    Pipeline design included design development drawings, draft and final technical memoranda; pipeline hydraulics included design development drawings, calculation draft and final technical memoranda. At the 60 percent complete level of the final design, Dean Ryan provided 60% percent of the preliminary design drawings and specifications; at the 90 complete level, Dean Ryan delivered the balance of the preliminary drawings and specifications. Dean Ryan was selected to prepare the final design drawings and specifications.

    During the design reviews and approval, a QA/QC project plan was developed at 30, 60 and 90 percent review phases documenting implementation of the QA/QC plan. Design computation review and coordination checking included a submittal of final design notebooks and internal Technical QA/QC reviews to the City at the 30%, 60% and 90% levels. Operations and Maintenance reviews included memoranda responding to CityÃs review comments following the 30%, 60% and 90% complete submittal reviews.

    A Dean Ryan produced Value Engineering (VE) Study at the 30 percent design level included materials to be presented to the VE team in addition to drawings, specifications, and cost estimates and memorandum responding to the VE recommendations. The Value Engineering Study at the 60 percent design level (NIC) included 60 percent materials to be presented to the VE team.

    Construction Cost estimates included the following: deviation and trending submittals including cost estimates supporting the deviation submittal and/or cost trend submittals; and preparation of 30 percent construction cost estimates for the construction of pipelines and appurtenances, excluding O&M costs. Dean Ryan also prepared final pre-bid construction cost estimates for the construction of pipelines and appurtenances, excluding O&M costs.